Converts project brief information into a DRAFT Class D (Schematic Design / Order-of-Magnitude) construction cost estimate report with an elemental cost breakdown, location and market-condition adjustments, tiered contingencies, and a clearly documented assumptions and exclusions list. Produces a report for the cost manager or QS to verify before presenting to the owner or design team.
Ask one question at a time. Wait for each answer before proceeding.
Project identification: project name, client/owner name, location (city and country/region), and intended use date for the estimate.
Project type: select the primary category:
Gross floor area: total GFA in m² or ft² (specify unit). For multi-building projects, list each building separately.
Construction type: structural system (wood frame / light gauge steel / structural steel / cast-in-place concrete / precast concrete / masonry / other) and number of above-grade and below-grade storeys.
Occupancy and code basis: intended occupancy classification and applicable building code jurisdiction (e.g., IBC 2024, NBCC 2020, AS 1170, Eurocode).
Scope inclusions: which of the following are in scope? (Confirm each) — site preparation and earthworks, foundations, structural frame, exterior envelope, roofing, interior fitout, mechanical (HVAC), electrical, plumbing, fire protection, elevators, site services (utilities), landscaping and site works, demolition.
Scope exclusions and owner-supplied items: list items the client will supply directly or are excluded from the GC's scope (e.g., FF&E, owner-procured equipment, telecom, security, art).
Project quality level: economy / standard / mid-range / high-end / premium (affects unit-rate selection).
Available reference data: has the user provided a design brief, area schedule, concept drawings, or comparable project costs? If yes, ask the user to share them now.
Confirm the scope summary with the user before proceeding.
Apply location cost indices to base rates:
Produce a table of cost elements. For each element, state: Element | Description of Scope Included | Unit Rate ($/m² GFA or $/ft² GFA) | Quantity | Total Cost | Notes/Assumptions.
Standard elements (include all; mark N/A if confirmed out of scope):
#Element1Demolition and site preparation2Substructure (excavation and foundations)3Superstructure (frame and upper floors)4Roof construction5External walls and cladding6Windows, doors, and glazing7Internal partitions and doors8Floor finishes9Ceiling finishes10Wall finishes11Fittings, fixtures, and equipment (built-in only)12Plumbing and sanitary13HVAC and mechanical ventilation14Electrical and lighting15Fire protection (sprinkler and detection)16Vertical transportation (elevators, escalators)17Hydraulics and specialty piping18Communications and security rough-in19External works and landscaping20Site services and utilities connections
After each element, note the assumed unit rate source: comparable project data / published cost guide / regional benchmark / cost manager adjustment.
Apply three tiers of contingency:
TierPurposeTypical RangeApplied RateDesign contingencyIncomplete design definition at schematic stage15–25% of construction costState applied %Construction contingencyUnforeseen conditions and minor scope changes5–10% of construction costState applied %Escalation contingencyCost movement between estimate date and tender/awardDepends on programState applied % and basis period
State the reasoning for each applied rate. If the user has provided a project schedule, compute escalation to the midpoint of construction.
Produce the DRAFT report:
text
DRAFT — FOR COST MANAGER REVIEW
PRELIMINARY COST ESTIMATE REPORT
Project: [PROJECT NAME]
Client: [CLIENT NAME]
Location: [CITY, COUNTRY]
Building Type: [TYPE]
GFA: [X] m² / ft²
Estimate Class: Class D — Schematic Design / Order of Magnitude
Estimate Date: [DATE]
Prepared by: [NAME / FIRM — to be completed by cost manager]
Status: DRAFT — Not for owner distribution until cost manager review
─────────────────────────────────────────────────────────────────────────
ELEMENTAL COST PLAN
─────────────────────────────────────────────────────────────────────────
[Elements table: # | Element | $/m² GFA | Quantity (m²) | Total ($) | Notes]
SUBTOTAL — CONSTRUCTION COST (ELEMENTS 1–20): $XXX,XXX
─────────────────────────────────────────────────────────────────────────
CONTINGENCIES
Design Contingency [X]% $XXX,XXX
Construction Contingency [X]% $XXX,XXX
Escalation Contingency [X]% $XXX,XXX
TOTAL CONSTRUCTION COST (INCL. CONTINGENCY): $XXX,XXX
─────────────────────────────────────────────────────────────────────────
PROJECT COST ADDITIONS (excluded from GC contract — for reference only)
Professional fees (design + QS) [%] $XXX,XXX
Authority fees and permits $XXX,XXX (allow)
FF&E and owner-supplied items [Stated scope exclusion]
Land (if applicable) [Not included]
TOTAL PROJECT COST (ORDER OF MAGNITUDE): $XXX,XXX
─────────────────────────────────────────────────────────────────────────
COST RATE SUMMARY
Construction cost / m² GFA: $X,XXX / m²
Construction cost / ft² GFA: $XXX / ft²
─────────────────────────────────────────────────────────────────────────
ASSUMPTIONS AND EXCLUSIONS LOG
[Numbered list]
INFORMATION GAPS AND OPEN ITEMS
[Numbered list — items that must be resolved before upgrading to Class C]
COST MANAGER REVIEW BLOCK
This report is a DRAFT Class D estimate. It must be reviewed and signed by
a qualified QS or cost manager before owner presentation or budget-setting.
Reviewer: ________________ Firm: ________________ Date: ________
Signature: ________________
Before outputting the report, confirm:
Single markdown document structured per the Phase 5 template. Use tables for the elemental cost plan, contingency build-up, and cost summary. Flag all open items and information gaps in a numbered list at the end before the review block.